Master Scheduler ed.saumell@att.net 305-915-0324 Professional Experience
Mr.
Saumell has amassed over twenty years of scheduling and cost controls
experience in Curtain Wall Manufacturing & Installation, Construction and
Nuclear Power. During his tenure, he was instrumental in the ongoing design
and development of Project Scheduling, Front End Documentation, Cost Loading,
Scope Development, and Bid Selection. Mr. Saumell’s experience goes beyond
the realm general scheduling duties. He has countless years of experience as
a Design Team Member handling all phase of Preconstruction and working under
the highest standards imposed by State and Federal Regulatory Agencies. The
amount of experience that Mr. Saumell has in Construction, Power Generation
and Nuclear Project Engineering serves as a true indicator of his limitless
abilities. Gamma USA, Inc. April 2013 to Present Miami, Florida - Master Scheduler In
charge of developing resource and cost loaded CPM schedules for multiple
projects throughout North America, from bidding, design, manufacturing,
installation and close-out. In charge of integrating Gamma’s schedules from
MS Projects Platform to a Master schedule using P6. The Spear Group March 2008 – March 2013 Miami, Florida - Senior Scheduler Florida Power &
Light – Senior Scheduler for FPL’s Turkey Point Nuclear Power
Station’s Road to Excellence Project which consists of 30 individual projects
($246.6 Million) Responsible for developing, maintaining, and updating the
resource loaded CPM project schedules from design and development through
construction / implementation phases. The schedules were created and
Maintained in P6, Bovis Lend Lease October 2006 to March 2008 Miami, Florida - Scheduler II Paramount Bay
Condominiums - Project Scheduler for a 50 story 4 building condominium
project ($163.2 Million) Responsible for developing, maintaining, and
updating the CPM project schedule from the design and development phase
through construction and included a detailed commissioning phase. The
schedule was created in P3 and maintained in P6. Kraft Construction May 2005 to October 2006 Naples, Florida - Master Scheduler & Cost
Analyst Cost Analyst Key
position held at Kraft Construction as a Design Team Member handling the
majority of preconstruction scheduling activities. Duties and
responsibilities begin during the development of new projects and follow
through to final completion. A major area of accomplishment is the
feasibility and cost analysis required for every new project that comes into
the company. Master
Scheduler Jasmine
Bay Condominiums (Estero, FL) – Project Scheduler for this
28 story 2 building condominium project ($140 Million). I was responsible for
the creation of an original template that would integrate the construction of
4 separate buildings on one small footprint for construction. I was a member
of the Design and Development Team attending OAC and subcontractor meetings.
All scheduling were created in Primavera SureTrak, Primavera Standard P3 and
converted to Primavera 5.0. Major areas of accomplishments were not limited
to scheduling, but encompassed the vast range of preconstruction Services. HHH
Middle School (Naples, FL) - Project Scheduler for this
120,000 square foot 2 story new school ($50 Million). I was associated with
this project from the design and development phase through construction.
Major areas of accomplishments included design and development of centralized
scheduling templates using Primavera Contractor. Three individual schedules
were concurrently published in Primavera Contractor, SureTrak, P3, and
converted to Primavera 5.0. Renaissance
Village (Naples, FL) - Senior Scheduler assigned to this
multi phase construction project ($105 Million). This project offered a
difficult challenge for multi phasing construction. The project was separated
into 4 separate phases to include its own buyout and completion for
individual phasing. It was necessary to maintain a Master Schedule to track
each project as its own WBS to be reported into an OBS file as a resource. Castillo
at West Shores (Pensacola, FL) - Senior Project Scheduler
for this twin tower high-rise project ($51 Million). I was associated with
this project as a fulltime Scheduler and participated from the design &
development through actual construction. The entire schedule was completed
using Primavera SureTrak 3.0 version b and maintained using Primavera 5.0.
The phasing demands associated with this project required a unique scheduling
solution. Rivo
Towers (Sarasota, FL) - Senior Project Scheduler for this 16
story condominium project ($123 Million). I was associated with this project
from the design & development stages through actual construction.
Schedules were completed and submitted using Primavera 3.0 version b. I was
responsible for submitting schedules for estimating, submittal, and
construction. Once my original construction schedule was published, I was
responsible for the weekly updates. North
Collier Hospital (Naples, FL) - Project Scheduler for this
6 story Hospital renovation ($32 Million). I was associated with this project
from the design and development phase through construction. Major areas of
accomplishments included design and development of centralized scheduling
templates using Primavera Contractor. Three individual schedules where
concurrently published in Primavera Contractor, SureTrak, and P3. High
Point Place (Ft. Myers, FL) – Project Scheduler for this
multi-phased Condominium Project ($267 Million). I was responsible for the
creation of an original template that would integrate the construction of 2
separate projects on one small footprint for construction. I was a member of
the Design and Development Team attending OAC and Subcontractor Meetings. All
scheduling was created in Primavera SureTrak and Primavera Standard P3. Major
areas of accomplishments were not limited to scheduling, but encompassed the
vast range multiple phases of mixed construction projects. APAC May 2002 to April 2005 Miami, Florida - Scheduler/Cost Controls Scheduler/Cost
Engineer working on the South Terminal Expansion Program, Miami International
Airport in Miami, Florida ($545 Million). Work with the Project and Program
Staff providing Scheduling and Contract Cost controls. Developed and maintain
resource loaded / cost loaded schedules and cost controls for projects
assigned to the international concourse. Performed Time Impact Analysis,
analyze the effects on critical path due to delays. Work with the Project
Staff in change order price analysis, claims and loss prevention. G.D. Barri and Associates July 2001 to April
2002 Oswego, New York - Scheduling Consultant In
charge of building, analyzing and maintaining the Constellation Nuclear Nine
Mile Point Power Station ISI and Erosion / Corrosion project Schedule using
Primavera Project Manager (P3). Worked closely with Project Manager and
project Team members to insure Schedule Goals and budgets were met.
Responsible to review Progress Schedule as reported by Team members and
prepared daily status reports and schedules for plant management. Florida Power & Light May 1992 to June
2001 Miami, Florida - Scheduler Develop
Online and Outage schedules/projects using Primavera Project Manager.
Modifying time lines and work schedules as necessary in order to maintain
critical path and cost overrun. Ensure schedule is man-loaded correctly using
Resource profile analysis. In addition, I prepared daily schedule status
reports for management. March 1985
to May 1992 Senior
Maintenance Planner Instrument
& Control Specialist Planned
trouble tickets using Passport Systems, Performed field investigation
verifying the validity of discrepancies, identifying work scope, parts
required, and any safety issues in order to ensure the successful completion
of the task. Planned PM work orders, ensuring all parts, procedures and
instructions were properly identified. Tracked all PM's verifying their
periodicity was properly maintained as required by the plant PM program.
Planned PM work orders, ensuring all parts, procedures and instructions were
properly identified. Tracked all PM's verifying their periodicity was
properly maintained as required by the plant PM program. Perform Preventive /
Corrective maintenance on plant installed equipment. Developed Calibration
Data Sheets used by the staff. Developed work maintenance instructions and
procedures utilized by the staff for the program. United States Army August 1976 to August 1980 Specialist
5 Avionics
Instrumentation Specialist Education
Miami Dade Community College A.S.,
Electronic Technology - 1984 Miami, Florida A.A., Business Administration - 1988 Knowledge: Primavera 6.0 Primavera P3e/c 4.0 Primavera P3 Project Planner SureTrak 3.0 V-B Primavera Expedition Primavera Contractor Prolog 6 Microsoft Projects Claim Digger Microsoft Office Suite |
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|